Skip to main content
Bellevue home
  • Bellevue Home
  • City Government
    • Boards, Commissions and Committees
    • City Code, Resolutions and Ordinances
    • City Council
    • Communications
    • Departments
    • East Bellevue Community Council
    • Hot Topics and Initiatives
    • Public Records Requests
    • Sister Cities
  • Departments
    • City Attorney's Office
    • City Clerk's Office
    • City Manager's Office
    • Communications
    • Community Development
    • Development Services
    • Emergency Management
    • Finance & Asset Management
    • Fire
    • Human Resources
    • Information Technology
    • Parks and Community Services
    • Police
    • Transportation
    • Utilities
  • Discover Bellevue
    • About Us
    • Bellevue Television
    • City News
    • Things to Do
    • Arts in Bellevue
    • Parks and Trails
    • Economic Development
  • Doing Business
    • Building and Zoning
    • Doing Business in Bellevue
    • Doing Business with Bellevue
  • Public Safety
    • Police
    • Fire
    • Emergencies and Extreme Weather
    • Emergency Preparedness
    • Municipal Court
    • Neighborhood Traffic Safety
    • Probation
    • Public Defenders
  • Resident Resources
    • ADA and Language Access Resources
    • Customer Assistance
    • Conflict Assistance
    • Diversity Advantage
    • Neighborhoods
    • Newcomers Guide
    • Permits, Parking and Utilities
    • Volunteering
City of Bellevue, WA Utilities
English Español 简体中文 繁體中文 日本語 한국어 Pусский Tiếng Việt

Water Main Program

Breadcrumb

  1. Home
  2. City Government
  3. Departments
  4. Utilities
  5. Utilities Projects
  6. Utilities Capital Projects
  7. Water Main Program
Utilities Services

How may I help you?

This is an artificial-intelligence (AI) chatbot designed to provide general information about various city topics. If you are having an emergency of any kind, please call 911 immediately. The chatbot is still learning about all of our services and may occasionally provide an incorrect answer.

Give Feedback
  • Increase Text Size
  • Decrease Text Size
  • Print
Opens in a new window Opens in a new window Opens in a new window
Copied to clipboard

Utilities Capital Projects

  • Capital Projects Proposed Budget
  • Clyde Hill 390 Reservoir Seismic Upgrade and Clyde Hill Pump Station Replacement Project
  • Clyde Hill Reservoir Improvement Project
  • Crossroads North and South Reservoir Recoating Project
  • Factoria Boulevard Stormwater Conveyance
  • Horizon View 2 Reservoir and Pump Station Project
  • Kelsey Creek/Lake Hills Culvert Project
  • Lake Hills Connector Fish Passage Improvements
  • Lakemont Blvd Culvert
  • Meydenbauer South Reservoir
  • Newport Sewer Basin Capacity Improvements
  • Newport Shores Sewer System Improvements
  • Pikes Peak Reservoir Replacement
  • Sewer Capital Investment Projects
  • Somerset 2 Pump Station Rehabilitation
  • Somerset Highlands Fire Flow Improvements
  • Somerset Reservoir Decommissioning Project
  • South Ridge Pump Station Improvements
  • Stormwater Capital Investment Projects
  • Valley Creek Culvert Replacement and Stream Restoration Project
  • Valley Creek at NE 20th Street Flood Control Project
  • Water Capital Investment Projects
  • Water Main Program
  • Watershed Management Plan

The City of Bellevue annual water main program replaces old, deteriorated, small-diameter pipe with new ductile water main pipe. The City replaces 5 miles of old water pipe each year to minimize and reduce risk of potential disruptions and address concerns of old infrastructure.

Although projects and field conditions vary, a general factsheet has been developed for reference on what to expect when a water main project goes to construction. Neighborhoods and existing conditions may deviate from expectations, but the City aims to minimize impacts where we can.

FAQs

Construction Impacts

Please note that other jurisdictions may have additional policies and permitting requirements when working in the Right-of-Way. The info below applies to the City of Bellevue.

Will I be able to access my property during construction?

Yes, the contractor is required to maintain access to properties. Site constraints may require additional coordination and possible delays in access. 

What will traffic control look like?

Flaggers will be present to safety direct cars through the project site. Partial lane closures will occur in applicable areas. Some site conditions may require a greater presence of traffic control.

Where will equipment be staged?

Equipment will be staged in the public Right-of-Way. Equipment will not block property access.

What will vehicular access to roads and properties look like on narrow roads?

Additional coordination for work timing will occur with homeowners for narrow, 1-lane roads. For locations where access is limited, the contractor would likely need to backfill or place steel plates during work hours for vehicular traffic. This may result in ~20-minute delays.

What size will the construction equipment be for smaller areas?

Smaller trucks and excavators will be used for narrow access roads. 

How will the road be restored?

Temporary Hot Mix Asphalt (HMA) will be poured first until permanent HMA is put in. Permanent HMA is much smoother than temporary HMA and will be poured before the end of the water main replacement project.

A future pavement project will consolidate all paving sites requiring a full-width road restoration. The City of Bellevue Utilities and Transportation department will coordinate road restoration sequencing when possible.

How will my yard be restored during water service connections?

Yards that were disturbed will be restored before finishing a neighborhood site. Once water services are replaced, paving will occur and final restoration will occur after. You may see some demobilization occur before new equipment arrives for these steps.

What are typical project working hours?

Typical working hours are 7:30am - 4:00pm, Monday through Friday. The construction contractor may apply for different working hours. For up-to-date working hours, contact the project inspector or contractor. 

How will I receive project and construction updates?

Postcard mailers will be sent throughout the design phase and 1 month before the start of construction. Additional notifications and coordination may occur for site-specific needs.

Water Shutdown

Please note all durations, occurrences, and ranges listed are typical numbers based on previous projects. Field conditions can affect typical estimates. We aim to minimize disruptions as much as possible and try to finish quicker, but sometimes exceptions happen. We recognize this is an inconvenience and we will work quickly to restore service once the work is complete.

What is a water main shutdown?

A water shutdown is a City-initiated water disruption to make repairs or new connections to the water system. For City projects, this is to connect the newly built pipe into the water system.

When do water main shutdowns occur?

Water main shutdowns typically occur between 8:30am – 5:00pm. Shutdowns do not occur on consecutive days (if there is more than 1) to the same properties and we try to avoid more than once a week.

What is a water service connection interruption?

A short water disruption occurs when the new individual water service is connected to your property. This disruption is typically 1 hour in duration but is often shorter.

What is the difference between a water main shutdown vs. a water service disruption?

A water main disruption affects the city’s larger pipeline that carries water to multiple homes and buildings. A water main shutdown is longer in duration and will affect sections of homes/buildings all at once.

A water service disruption affects the service pipe to individual homes and buildings. A water service disruption is shorter in duration and will affect singular buildings at a time.

How many water main and service disruptions should I anticipate?

Typically, 1 mandatory water shutdown is required to connect the new water main into the water system and 1 mandatory short water disruption to connect your individual service into the system. However, additional disruptions may occur depending on the configuration of the water system and field

When will water shutdowns occur and how will I be notified?

Once construction begins, you will be provided with more details on the estimated duration, day of shutdowns, and other details prior to any shutoffs. 

All shutdowns will provide notification through courtesy notices (door tags) at least 2 days in advance of any planned shutdown. For secure buildings, such as apartments, courtesy notices will be left with the building manager.

How can I prepare for a water shutdown?

For info on how to prepare, the Utilities department has a general webpage available: Water Main Shutdowns

PROJECT CONTACTS:

For specific or additional questions about water main projects in your area, project contacts are included below.

To locate which Year and Phase your neighborhood is included in, refer to the Capital Projects Dashboard Map.

PROJECT NAMESTATUSPROJECT MANAGERCONSTRUCTION INSPECTOR
2025 Phase 1ConstructionJim Stockwell
JStockwell@bellevuewa.gov 
425-452-4868
Weston Dalfrey
WDalfrey@bellevuewa.gov
425-452-4125
2025 Phase 2ConstructionJim Stockwell
JStockwell@bellevuewa.gov 
425-452-4868
Robert Rudd
RRudd@bellevuewa.gov 
425-452-42422
2026 Phase 1ConstructionJim Stockwell
JStockwell@bellevuewa.gov 
425-452-4868
Chris Pierson
CPierson@bellevuewa.gov 
425-452-6109
2026 Phase 2ConstructionAli Sabeeh
ASabeeh@bellevuewa.gov 
425-452-7663
Weston Dalfrey
WDalfrey@bellevuewa.gov
425-452-4125
2026 Phase 3DesignChristina Pham  
cpham@bellevuewa.gov 
425-452-4284
Will be updated in construction
2027 Phase 1DesignJim Stockwell
JStockwell@bellevuewa.gov 
425-452-4868
Will be updated in construction
2027 Phase 2DesignAli Sabeeh
ASabeeh@bellevuewa.gov 
425-452-7663
Will be updated in construction
2027 Phase 3DesignChristina Pham  
cpham@bellevuewa.gov 
425-452-4284
Will be updated in construction

 

 

 

Utilities

Michaelene Fowler
Public Information Officer

Telephone
425-452-6145
Email
mfowler@bellevuewa.gov

Reasonable Accommodation

For alternate formats, interpreters, or reasonable modification requests please phone at least 48 hours in advance 425-452-6800 (voice) or email servicefirst@bellevuewa.gov. For complaints regarding modifications, contact the City of Bellevue ADA, Title VI, and Equal Opportunity Officer at ADATitleVI@bellevuewa.gov.

City of Bellevue sealCity of Bellevue, WA

  • 450 110th Avenue NE
  • Bellevue, WA 98004
  • Directions to City Hall
  • 425-452-6800
  • servicefirst@bellevuewa.gov
  • Contact Us / City Directory
  • Monday - Friday 8 a.m. - 4 p.m.

Footer Menu Contacts

  • MyBellevue Customer Assistance
  • Careers
  • ADA/Title VI Notices

Languages

  • English
  • Español
  • 简体中文
  • 繁體中文
  • 日本語
  • 한국어
  • Pусский
  • Tiếng Việt

Request a Translation

  • Request a Translation
  • اطلب ترجمة
  • 申请翻译
  • 要求翻譯
  • अनुवाद का अनुरोध करें
  • 翻訳をリクエストする
  • 번역 요청
  • درخواست ترجمه
  • ਅਨੁਵਾਦ ਦੀ ਬੇਨਤੀ ਕਰੋ
  • Запрос на перевод
  • Solicitud de traducción
  • అనువాదం అడగండి
  • ترجمےکے لئے ایک درخواست
  • Yêu cầu bản dịch
  • ትርጉም መጠየቅ

Social Media

© 2024 City of Bellevue | All Rights Reserved. | ADA/Title VI Notices | Terms of Use | Privacy Policy | Site Map | AI Policy