The City of Bellevue installed a new sewer pipeline in the Newport Shores neighborhood. This work will help reduce the risk of sewer backup during large storm events.

The project completed construction in the summer of 2023.

Map showing Newport Sewer Basin Capacity Improvements Project location

Why is this project needed?

During large rain events, excess storm water can seep into the aging sewer system through small cracks. This rain infiltration can overwhelm the capacity of the system and lead to the risk of wastewater backups in low-lying homes. Bellevue crews previously managed this problem by using vacuum trucks to transport excess wastewater to the Newport Pump Station. Relying on this manual operation was not ideal or a long-term solution.

Project solution

Rather than crews manually transporting wastewater flows during rain events, the construction of a new sewer “force” main will improve both capacity and reliability of the current sewer system by moving wastewater flows away from under-capacity areas with the use of portable pumps.

Project benefits

With the new sewer line, residents in this neighborhood will see improvements in wastewater management and environmental protection, reduced risk of sewer backup, and safer access into and out of the neighborhood during severe storm events.

Project timeline

  • Design and Permitting
    January 2021 – December 2022
  • Public engagement
    January 2021 – October 2023
  • Bid Advertisement
    September 2022
  • Force Main Construction
    January 2023 – July 2023
  • Grind and Overlay Construction
    August 2023 – September 2023

Opportunities for public input

The project team held a virtual community meeting in February 2022 to overview the project and potential impacts. View the virtual presentation in the "Related documents" section below.

Related documents