Bellevue Utilities water capital projects ensure current and future generations have reliable drinking water services. The 2025-2030 Adopted Utilities Capital Improvement Plan (CIP) is a budget for critical utility system infrastructure improvements that will be implemented in the next six years. The following table shows the Water Utility capital projects in the 2025-2030 Utilities Capital Improvement Plan (CIP) that was adopted by the City Council in November 2024.
| Water CIP Programs | Description | Reason | Implementation | 2025-2030 CIP Budget |
| Water Main Replacement | Replace 5 miles of old water pipe each year | Renewal and Replacement | 2025-2030 | $107,755,000 |
| Pressure Reducing Valve (PRV) Rehabilitation | Replace PRV stations; add pressure and flow monitoring | Renewal and Replacement | 2025-2030 | $8,138,000 |
| Reservoir Rehabilitation or Replacement | Replace drinking water reservoirs that have structural deficiencies and provide recoating for existing reservoirs | Renewal and Replacement | 2025-2030 | $5,447,000 |
| Water Pump Station Rehabilitation or Replacement | Rehabilitate or replace water pump stations | Renewal and Replacement | 2025-2030 | $10,777,000 |
| Replacement of Large Commercial Water Meter Vaults | Replace four vaults for high-volume commercial water meters every year, due to age, access and safety problems | Renewal and Replacement | 2025-2030 | $3,962,000 |
| Water Supply Inlet Rehabilitation | Rehabilitate water supply inlets from Cascade and SPU transmission pipes | Renewal and Replacement | 2025-2030 | $1,219,000 |
| Water System Planning | Evaluate and develop future CIP needs | Renewal and Replacement | 2025-2030 | $796,000 |
| SCADA System Upgrade | Upgrade the water system telemetry infrastructure | Renewal and Replacement | 2025-2030 | $944,000 |
| 170th Pl SE Pressure Improvements | Resolve deficient water pressure on 170th Pl SE | Renewal and Replacement | 2025-2030 | $288,000 |
| Increase Drinking Water Storage Availability for West Operating Area | Planning and design for future reservoir needed by 2030 | Capacity for Growth | 2025-2030 | $34,037,000 |
| Maintenance and Operations Yard | Design and construction of new operations and maintenance facility | Operational Efficiency | 2025-2030 | $4,943,000 |
| Somerset Highlands Capacity Improvements | Improve fire flow deficiency in Somerset Highlands neighborhood | Renewal and Replacement | 2025-2030 | $5,287,000.00 |
| Groundwater Well Improvements | Rehabilitate existing groundwater wells for emergency supply | Emergency Water Supply | 2025-2030 | $4,143,000 |
| Total 2025-2030 Water CIP Budget = | $178,306,000 |