Water Capital Investment Projects

Header Image
Project Banner 6-20-17.jpg
Water main replacement program.

Bellevue Utilities water capital investment projects ensure that current and future generations have reliable drinking water services. These projects are proposed in the 2021-2027 Utilities Capital Investment Project (CIP) plan, subject to approval by the City Council in November or December 2020.

Capital Investment Project

Description

Reason

Implementation

Cost

Water Main Replacement

Replace 5 miles of old water pipe each year

Renewal and Replacement

2021 - 2027

$81,290,000

Pressure Reducing Valve (PRV) Rehabilitation

Replace 3 PRV stations per year; add pressure and flow monitoring

Renewal and Replacement

2021 - 2027

$6,000,000

Minor (Small) Water Capital Improvement Projects

Miscellaneous projects or repairs to resolve deficiencies or improve efficiency

Renewal and Replacement

2021 - 2027

$1,290,000

Reservoir Rehabilitation or Replacement

Replace drinking water reservoirs that have structural deficiencies and provide recoating for existing reservoirs

Renewal and Replacement

2021 - 2027

$23,380,000

Water Pump Station Rehabilitation or Replacement

Rehabilitate or replace one water pump station every other year

Renewal and Replacement

2021 - 2027

$7,040,000

Replacement of Large Commercial Water Meter Vaults

Replace four vaults for high volume commercial water meters every year, due to age, access and safety problems

Renewal and Replacement

2021 - 2027

$3,350,000

Water Service Line & Saddle Replacement Program

Replace water service lines from the water main to the right-of-way, that are in danger of failing

Renewal and Replacement

2021 - 2027

$640,000

Increase Drinking Water Storage Availability for West Operating Area

Planning and design for future reservoir needed by 2030

Capacity for Growth

2021 - 2027

$4,080,000

Water Facilities for NE Spring Blvd Multi Modal Corridor

Construct new water facilities in this new transportation corridor as it develops

Capacity for Growth

2021 - 2027

$2,850,000

Maintenance and Operations Yard

Design and construction of new operations and maintenance facility

Service Enhancement

2021 - 2027

$2,667,000

SCADA System Upgrade

Upgrade the water system telemetry infrastructure

Renewal and Replacement

2021 - 2027

$1,410,000

170th Pl SE Pressure Improvements

Resolve deficient water pressure on 170th Pl SE

Renewal and Replacement

2021 - 2023

$1,080,000