On March 11, 2021, PSE applied for two land use permits for the North Segment:
- Conditional Use Permit File # 21-104991-LB (CUP)
- Critical Areas Land Use Permit File # 21-104989-LO (CALUP)
A public hearing before the city's Hearing Examiner is scheduled for Nov. 9 at 6 p.m. at Bellevue City Hall (450 110th Avenue NE, Bellevue, WA). This public hearing is a Pre-Decision hearing on PSE's application for CUP approval.
The public hearing will be conducted in a hybrid manner with both in-person and virtual attendance options. The public may participate in the hearing by providing oral comments in person at Bellevue City Hall in the Council Chambers, connecting virtually via Zoom, or by submitting written comments. Written comments can be submitted via e-mail to the Hearing Examiner and must be received by 3 p.m. on Thursday, Nov. 9.
Sign-up online to provide oral testimony at the public hearing. Sign-up closes at 3 p.m. on Thursday, Nov. 9. Join virtually via Zoom (Passcode: 216461).
Resources
Project File
Attachment B - North Bellevue Segment CUP Analysis
Attachment C - Vegetation Management Plan
Attachment D - Map UT-7 Utilities
Attachment E - Comment Response Letter
Attachment F - July 11, 2023 Reliability Certification
Attachment G - 2023 SEPA Addendum
Pole Finishes Report North Segment
Mitigation, Restoration or Enhancement Plan
NOA 21-1049910-LB and 21-104989-LO Combined
City Staff Report and Attachments
Attachment B - North Bellevue Segment CUP Analysis with Alternative Siting Analysis
Attachment C - Vegetation Management Plans
Attachment D - Map UT-7 Utilities
Attachment E - Watershed March 1, 2023 Response Letter
Attachment F - July 11, 2023 Reliability Certification
Attachment G - 2023 SEPA Addendum
Initial North Segment Permit Plans and Reports
Included in the city file for the North Segment permit applications are the following documents: