Benefits
The project provides pedestrian and bicycle access to the future light rail station at 120th Avenue NE. Its design is compatible with nearby development and includes the following safety improvements along 124th Avenue NE, between NE 8th and NE 12th Streets (refer to map and construction alert):
- Sidewalk with curb ramp improvements on the west side of 124th Avenue NE, from NE 8th Street to NE 10th Place;
- Median with a flashing beacon and mid-block crossing south of NE 10th Place; and,
- Eight new streetlights on both sides of 124th Avenue NE (to be installed at a later date).
Schedule
- October: Project complete
- June 2021: Project substantially completed; awaiting final paving
- February 2021: Construction pause scheduled for fabrication of street lights
- December 2020: Construction start
- December 2018: Capital budget approved funding safety improvements
- October/November 2018: Present recommendations to City Council
- September/October 2018: Present recommendations to Transportation Commission
- September 2018: Survey results mailer sent
- August 2018: Survey residents
Funding
The project is only funded for the safety improvements. Approved 2021-2027 Capital Investment Program Budget Sheet.
Outreach materials
- Construction alert mailer (November 2020)