124th Ave NE: Spring Blvd to Ichigo Way

Header Image
Bel-Red Character Sketch - 130th Ave.jpg

As part of the 124th Avenue Corridor Improvement Project to support planned growth and development in the BelRed area, improve circulation and accommodate an East Link light rail undercrossing, the City of Bellevue plans to:

Portion of 124th Ave NE closed starting Sept. 9, 2019

Starting Monday, Sept. 9 and lasting through June 2020, a portion of 124th Ave NE between NE 12th Street/Bel-Red Road and Northup Way will be closed to through traffic. The closure is needed to build a bridge to allow for the East Link light rail vehicles to pass underneath. Access to businesses along 124th Ave NE will be maintained during the closure from either direction.

Following the completion of the bridge, single lane closures on 124th Ave NE between NE Spring Blvd and Ichigo Way will be needed to complete the remainder of the work.

Benefits

The project will enhance access and circulation for cars, transit, freight, pedestrians and bicyclists.

Schedule

  • Sept. 9, 2019 through June 2020: A portion of 124th Ave NE between NE 12th Street/Bel-Red Road and Northup Way will be closed. Construction continues through 2020.
  • Aug. 2019: Contract awarded to Interwest Construction Inc. 
  • 2017: Funding finalized through a Federal Transportation Infrastructure Finance and Innovation Act (TIFIA) loan from the U.S. Department of Transportation.

Funding

The total project budget of $33 million is partially funded by Washington State Transportation Improvement Board (TIB) fund and Sound Transit's East Link light rail project.