The permit review timelines below outline the city’s established timeframes for reviewing permit applications. This information provides the community with greater transparency and predictability, while also helping Development Services identify patterns and trends that guide ongoing improvements.
The process of obtaining a plan review permit requires applicant and reviewer interaction. The length of time leading up to permit issuance depends on several factors:
- Completeness, accuracy and clarity of the plans and application from the individual applying for the permit.
- Parcel, property issues and building site conditions.
- Responsiveness of the property owner, permit applicant or acting delegate such as an architect, engineer or contractor to answer plan reviewer comments.
- Existing permit volume or workload of city staff at the time of the application's submission.
- The level of complexity or extent of work proposed, like projects requiring a SEPA determination, projects requiring a third-party structural review, etc.
Permitting Review Timelines
The city and its representatives provide review timelines for the following permit disciplines, folder types and descriptions along with supporting information. Actual review times will vary.
- Discipline: Development Services permitting divisions overseeing plan review for Building (BLDG), Clear & Grade (C&G), Fire, Land Use (LU), Right-of-Way (ROW), Transportation (TRAN), Utilities (UTIL).
- Folder Type: A two-letter designation used by staff to classify permits. The first letter reflects the review discipline, with some exceptions. The second letter is for identification of the folder type or the application's scope or work.
- Folder Description: Describes the Folder Type in the city's permitting database and provided as a way for applicants to discuss permit questions with city Development Service staff.
- Type: Further describes or delineates application work when it results in different permit review timelines.
- First Review Decision (FRD): Describes the duration in number of days in which the reviewer should complete their first review of the project. Applications are either approved or revisions are requested.
- Permit Revision Cycles (REV): May be necessary after the first review decision where the applicant must revise or respond to questions and resubmit permit documents. Revisions may be shorter in duration but will continue until the application meets all requirements and project review is complete.
- Over-the-Counter (OTC): Permitting for projects that do not need plan review and can typically be turned around within one day. OTC permits are excluded from the list of proposed permit review timelines.
- Without Major Project: The permit application exists independent of a larger project or without a known relationship to other permits in review.
- With Major Project: The permit application exists as part of a major or medium commercial project. Due to the project scope and complexity of submitted plans, longer permit review timelines are anticipated.
Building
The following permitting review timeline targets relate to applications associated with building permits.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| BB | Major Commercial Project | 56 | 21 |
| BE | Demolition | 14 | 10 |
| BG | Electrical Plan Review Without Major Project | 14 | 10 |
| BG | Electrical Plan Review With Major Project | 35 | 14 |
| BH | Detention Vault | 28 | 14 |
| BL | Mechanical Plan Review Without Major Project | 14 | 10 |
| BL | Mechanical Plan Review With Major Project | 35 | 14 |
| BM | Medium Commercial Project | 28 | 14 |
| BO | Plumbing Plan Review Without Major Project | 14 | 10 |
| BO | Plumbing Plan Review With Major Project | 35 | 14 |
| BR | Single Family Addition | 14 | 10 |
| BS | Single Family | 21 | 14 |
| BU | Single Family Remodel Plan Review | 14 | 10 |
| BV | Shoring Permit | 28 | 14 |
| BW | Minor Commercial Project | 14 | 10 |
| BY | Tenant Improvement - New Use | 21 | 14 |
| BZ | Tenant Improvement Plan Review | 14 | 10 |
| MH | Middle Housing New | 21 | 21 |
Clearing and Grading
The following permitting review timeline targets relate to applications associated with clearing and grading permits.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| GA | Minor Clearing & Grading | 14 | 10 |
| GB | Landscape Vegetation | 21 | 14 |
| GD | Clearing & Grading | 42 | 21 |
| GE | Plat Infrastructure | 42 | 21 |
| GT | Tree Removal Only | 10 | 7 |
Fire
The following permitting review timelines relate to applications associated with fire permits.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| FA | Electrical Fire Alarm Without Major Project | 14 | 10 |
| FA | Electrical Fire Alarm With Major Project | 35 | 14 |
| FB | Fire Sprinkler Systems Without Major Project | 14 | 10 |
| FB | Fire Sprinkler Systems With Major Project | 35 | 14 |
| FC | Single Family Fire Sprinklers | 14 | 10 |
| FD | Underground Sprinkler Mains Without Major Project | 14 | 10 |
| FD | Underground Sprinkler Mains With Major Project | 35 | 14 |
| FE | Fire Service Systems Without Major Project | 14 | 10 |
| FE | Fire Service Systems With Major Project | 35 | 14 |
| FF | Fixed Fire Suppression Systems Without Major Project | 14 | 10 |
| FF | Fixed Fire Suppression Systems With Major Project | 35 | 14 |
| FH | Smoke Control System | 56 | 21 |
Land Use
The following permitting review timeline targets relate to applications associated with land use permits.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| CD | Wireless Communication Facility on Private or Public Property | 28 | 14 |
| DA | Land Use Interpretation | 42 | 21 |
| DB | Preapplication Conference | 42 | 14 |
| DC | Predevelopment Services | 14 | 10 |
| DD | Reasonable Accommodation | 14 | 10 |
| DG | Zoning Status | 10 | 7 |
| GJ | Clearing & Grading in Critical Areas | 35 | 14 |
| LA | Administrative Conditional Use | 28 | 14 |
| LB | Conditional Use | 56 | 21 |
| LD | Design Review | 56 | 21 |
| LE | Environmental Impact Statement | 42 | 21 |
| LF | Final Short Plat | 21 | 14 |
| LG | Final Plat | 21 | 14 |
| LH | Home Occupation | 21 | 14 |
| LI | Land Use Approval Amendment | 35 | 14 |
| LJ | Land Use Exemption | 21 | 14 |
| LK | Planned Unit Development | 56 | 21 |
| LL | Preliminary Plat | 56 | 21 |
| LM | Preliminary SEPA Review | 35 | 21 |
| LN | Preliminary Short Plat | 42 | 21 |
| LO | Critical Areas | 42 | 21 |
| LP | Master Development Plan | 56 | 21 |
| LQ | Rezone | 56 | 21 |
| LR | Temporary Use | 14 | 10 |
| LS | Variance | 35 | 21 |
| LT | Vendor Cart | 14 | 10 |
| LV | Child Care Registration | 14 | 10 |
| LW | Boundary Line Adjustment | 28 | 14 |
| LY | Noise | 10 | 7 |
| LZ | Temporary Encampment | 21 | 14 |
| SA | Permanent Sign | 14 | 10 |
| SC | Temporary Sign | 14 | 10 |
| WA | Conditional Use Shoreline Management | 42 | 21 |
| WD | Shoreline Exemption | 28 | 14 |
| WE | Shoreline Exemption with SEPA | 35 | 14 |
| WG | Substantial Shoreline Development | 21 | 35 |
Right of Way (ROW)
The following permitting review timeline targets relate to applications associated with right of way. There are no type designations for this discipline.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| TE | ROW Street Use | 14 | 10 |
| TG | ROW Single Family | 14 | 10 |
| TJ | ROW Franchise | 14 | 10 |
| TK | ROW Government | 14 | 10 |
| TN | ROW Commercial Development | 14 | 10 |
Utilities
The following permitting review timeline targets relate to applications associated with utilities permits.
| Folder Type | Folder Description | First Review Decision Days | Revision Cycle Days |
|---|---|---|---|
| UA | Side Sewer Connection | 7 | 7 |
| UB | Storm connection | 7 | 7 |
| UC | Water Service | 7 | 7 |
| UE | Utility Extensions | 42 | 21 |