Nhảy đến nội dung

Take Bellevue Utilities Quick 3-minute Survey

Tell us what we are doing well and where we can improve. Your feedback helps shape future utility services for our growing community. Complete the survey and tell your neighbors by April 30: bit.ly/Bellevue-Utilities-Survey

Bellevue home
  • Bellevue Home
  • City Government
    • Boards, Commissions and Committees
    • City Code, Resolutions and Ordinances
    • City Council
    • Communications
    • Departments
    • East Bellevue Community Council
    • Hot Topics and Initiatives
    • Public Records Requests
    • Sister Cities
  • Departments
    • City Attorney's Office
    • City Clerk's Office
    • City Manager's Office
    • Communications
    • Community Development
    • Development Services
    • Emergency Management
    • Finance & Asset Management
    • Fire
    • Human Resources
    • Information Technology
    • Parks and Community Services
    • Police
    • Transportation
    • Utilities
  • Discover Bellevue
    • About Us
    • Bellevue Television
    • City News
    • Things to Do
    • Arts in Bellevue
    • Parks and Trails
    • Economic Development
  • Doing Business
    • Building and Zoning
    • Doing Business in Bellevue
    • Doing Business with Bellevue
  • Public Safety
    • Police
    • Fire
    • Emergencies and Extreme Weather
    • Emergency Preparedness
    • Municipal Court
    • Neighborhood Traffic Safety
    • Probation
    • Public Defenders
  • Resident Resources
    • ADA and Language Access Resources
    • Customer Assistance
    • Conflict Assistance
    • Diversity Advantage
    • Neighborhoods
    • Newcomers Guide
    • Permits, Parking and Utilities
    • Volunteering
City of Bellevue, WA Transportation
English Español 简体中文 繁體中文 日本語 한국어 Pусский Tiếng Việt

124th Ave NE: Ichigo Way to Northup Way

Breadcrumb

  1. Nhà
  2. 124th Ave NE: Ichigo Way to Northup Way
bellevue home

How may I help you?

This is an artificial-intelligence (AI) chatbot designed to provide general information about various city topics. If you are having an emergency of any kind, please call 911 immediately. The chatbot is still learning about all of our services and may occasionally provide an incorrect answer.

Give Feedback
  • Print
Opens in a new window Opens in a new window Opens in a new window
Copied to clipboard

Translated Pages Navigation

  • Chào Mừng
Header Image
Bel-Red Character Sketch - 130th Ave.jpg

Project Details

124th NE Ichigo Way to Northup Way project which began construction in June 2023 is now open. Improvements to this section of 124th Avenue Northeast, from Ichigo Way (formerly Northeast 18th Street) to Northup Way, included raising the roadway and widening it to five lanes. Other upgrades: a multi-purpose pathway on the west side of 124th, between Northeast 16th Street and Ichigo Way only, and sidewalks on both sides of the roadway, separated from the street by landscape planters and construct a culvert that fish and wildlife can navigate (full project description and budget information).

Crews are working to install railings and fences, finish up landscaping elements and complete minor work items. The project is estimated to be substantially complete in spring 2025.

Map of 124th Avenue Northeast from future Northeast Ichigo Way to Northup Way project
Click on image to enlarge

Benefits

The 124th Avenue Northeast project will enhance access and circulation for cars, transit, freight, pedestrians and bicycles between Downtown Bellevue, Wilburton and the BelRed area. It will accommodate future growth and new land uses in the area and ensure coordinated design, implementation and appropriate cost sharing with the East Link light rail project.

Schedule

  • Spring 2025: Substantial project completion
  • Fall 2024: Anticipated construction completion
  • March 2023: Construction begins
  • October 2022: Construction contract awarded to Active Construction Inc.
  • 2017: Funding finalized through a Federal Transportation Infrastructure Finance and Innovation Act (TIFIA) loan from the U.S. Department of Transportation

Funding

Total project budget of $41.1 million is partially funded by a TIFIA loan. Approved 2021-2027 Capital Investment Program Budget Sheet.

Outreach materials

  • Construction alert (June 2023)
  • Construction alert (March 2023)
  • Electrical tower replacement/monopole installation construction alert (September 2020)
  • Roadway cross-section diagram
  • Urban design elements diagram
image of 124th Avenue Northeast, from Ichigo Way to Northup
Alerts

Receive email or text updates on this project.

Subscribe

Contact

Marina Arakelyan, PE
Project Manager

Điện thoại
425-452-4632
Email
marakelyan@bellevuewa.gov
Mạng xã hội

Construction contact

Hernann Ambion

Construction Outreach Consultant

Điện thoại
425-241-8774
Email
124thaveproject@bellevuewa.gov

Hỗ Trợ Hợp Lý

Để nhận định dạng thay thế, yêu cầu phiên dịch viên hoặc nếu có yêu cầu sửa đổi hợp lý, vui lòng gọi điện trước ít nhất 48 giờ theo số 425-452-6800 (cuộc gọi thoại) hoặc gửi email tới servicefirst@bellevuewa.gov. Đối với các khiếu nại liên quan đến các sửa đổi, vui lòng liên hệ với ADA của Thành Phố Bellevue ADA, Tiêu Đề VI và Nhân Viên Cơ Hội Bình Đẳng theo địa chỉ ADATitleVI@bellevuewa.gov.

City of Bellevue sealCity of Bellevue, WA

  • 450 110th Avenue NE
  • Bellevue, WA 98004
  • Trực tiếp đến Tòa Thị Chính
  • Thứ Hai – Thứ Sáu: 8 giờ sáng – 4 giờ chiều

Footer Menu Contacts

  • MyBellevue Hỗ Trợ Khách Hàng
  • Nghề Nghiệp
  • ADA/Thông Báo về Tiêu Đề VI

Ngôn ngữ

  • English
  • Español
  • 简体中文
  • 繁體中文
  • 日本語
  • 한국어
  • Pусский
  • Tiếng Việt

Yêu cầu bản dịch

  • Request a Translation
  • اطلب ترجمة
  • 申请翻译
  • 要求翻譯
  • अनुवाद का अनुरोध करें
  • 翻訳をリクエストする
  • 번역 요청
  • درخواست ترجمه
  • ਅਨੁਵਾਦ ਦੀ ਬੇਨਤੀ ਕਰੋ
  • Запрос на перевод
  • Solicitud de traducción
  • అనువాదం అడగండి
  • ترجمےکے لئے ایک درخواست
  • Yêu cầu bản dịch
  • ትርጉም መጠየቅ

Mạng xã hội

© 2024 City of Bellevue | All Rights Reserved. | ADA/Title VI Notices | Terms of Use | Privacy Policy | Site Map | AI Policy