    The Downtown Park Median Expansions and Crossing project is an extension of the Downtown Park Complete the Circle and Inspiration Playground projects, finished in 2017. The roadway and sidewalk improvements will enhance safety and provide better accessibility for people traveling to the park. 

    Downtown Park Crosswalks project map

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    Project features

    • New median on 100th Ave. NE, between NE 1st Street and NE 4th Street
    • Mid-block crossing and sidewalk rebuild on NE 1st Street, between 100th Ave. NE and 102nd Ave. NE
    • Median and crosswalk rebuild on NE 2nd Street at NE 103rd Ave. NE

    Traffic impacts

    Expect daily lane closures on 100th Ave. NE and NE 1st Street. Sidewalks will be closed near construction zones. Detours will be in place. 

    Funding

    Construction cost: $402,000

    Schedule

    Work is scheduled to begin in March and end in May 2020